Pharmaceutical Start‑up
For laboratories and manufacturing sites. From empty shell to first release.
Permits & Accreditations.
Current engagement: QC testing laboratory
Twenty-six permits, registrations, and accreditations stand between an empty building and a first sample. These six are the most important in each category, the ones that gate whether the lab can open.
-
01
Building & Operations
Commercial Certificate of Occupancy
No one works in the building until it is issued. Every building, electrical, HVAC, plumbing, and fire approval rolls up into it.
Issued by Local municipalityTargetBefore February 1, 2027 -
02
Water & Environmental
Industrial Wastewater Pretreatment Permit
Lab sinks and instrument drains discharge to the city sewer. This permit sets what the lab may send down the drain.
Issued by Local municipalityTargetOctober 2026 -
03
Gas Storage & Generator
Hazardous Materials and Flammable Liquid Storage Permit
QC chemistry runs on solvents and reagents. Storage quantities, cabinets, and room limits are set here.
Issued by Local municipalityTargetDecember 2026 to January 2027 -
04
Waste Management
U.S. EPA Hazardous Waste Generator ID
A generator must hold an EPA ID before any hazardous waste leaves the site, so spent solvents cannot be shipped without it.
Issued by State environmental agencyTargetSeptember 30, 2026 -
05
Quality & Laboratory
ISO/IEC 17025 Accreditation
The international standard for testing laboratory competence. Clients and regulators use it to trust the lab’s results.
Issued by Accreditation body (A2LA or ANAB)TargetNovember 2026 -
06
Global Regulatory
FDA Establishment Registration and cGMP
FDA counts analytical testing of drugs as manufacturing under 21 CFR 207, so the lab registers and operates to cGMP under Part 211.
Issued by U.S. Food and Drug AdministrationTargetBefore client release testing
Road to first sample.
- Sep 30, 2026Design freeze
- Sep 30, 2026Building, trade, and EPA ID permit submissions
- Oct 2026Air quality, stormwater, and wastewater submissions
- Nov 2026ISO/IEC 17025 application and proficiency testing enrollment
- Nov 27, 2026Cleanroom installation
- Dec 15, 2026Equipment procurement deadline
- Dec 2026 to Jan 2027Fire inspection, hazard sign-off, and high-pressure gas line approval
- Jan 22, 2027Cleanroom, biosafety cabinet, and IQ/OQ/PQ validation
- Feb 1, 2027First QC chemistry sample
- Mar 1, 2027Full facility launch
Ready when you are.
Engagements by retainer or project. Mutual NDA first.
Or email consulting@tjsmgmt.com or call (610) 653-8362
Explore
Pharmaceutical Consulting
Back to compliant. And provably so.